Y2K White Paper
HON HAI PRECISION IND. CO., LTD.
Central Y2K Execution Team
APRIL, 1999
(This document has been translated from Chinese for the English speaking reader.)
-
INTRODUCTION
-
GOAL
-
STRATEGY
- Top to Down
- Down to Top
-
ACTION
- Y2K Project Organization
- Y2K Project Management Procedure
- Y2K Project Contents
- Inventory
- Risk Assessment
- Recovery Plan and Executing
- Contingency Plan
- Testing
- Internal Auditing
- Y2K Project Progress
- Y2K Initial Budget
-
APPENDIX: High Risk Date Tests
-
INTRODUCTION
the Information Technology Division
presents this proposal to be the solution that may solve the Millennium Bug existing in
FOXCONN systems. Included in this document are goals and strategies of this project,
methods adopted, and the contingency plan measurement.
-
GOAL
- This project proposes solutions and contingency measures to each division and
department, helping them to solve the Millennium Bug in schedules, and to minimize the
inconvenience and impact.
- In addition to computer systems, the embedded systems also need to be investigated in
detail.
-
STRATEGY
- Top to Down
Awareness of Y2K
Education & Training of Y2K
Y2K Project Plan
FOXCONN Y2K Project One-Page
Audit Plans
- Down to Top
Detail the Responsibility of Facility Management
Y2K Organization
Propose Y2K Test Schedule and Tool and Methodology
Inventory & Assessment Report
Risk Evaluation & Budget
Recovery Plan
Emergency Plan
Y2K Commitment from Vendors
RETURN TO TOP
-
ACTION
- Y2K Project Organization

RETURN TO TOP
- Y2K Project Management Procedure

RETURN TO TOP
- Y2K Project Contents
- Inventory

The most important and basic step for the Y2K Project, is to control all internal
software & hardware systems in the office, including information & non-information
systems. The more complete inventory of these systems, the easier its future risk
assessment & and subject recovery. It will also help to substantiate the problem range
of Y2K.
RANGE
Information systems
Systematic documents (or detailed lists): Most brochures & records of recovery are
included. Referring to risk assessment. All lists have to be filled in its document title
& published date as well.
Systematic environment: As much as information facilities & operation systems
should be completely evaluated instead of ignoring them, ex: PC, Server, voice mail
system, Database, WAN, LAN, telephone exchange, accumulating system, Monitors
etc.
Applied system (concerned with dates): All software in sets, operation software,
self-designed ort their names, manufactures & issued dates.
Available labor resources: All contact details and telephone numbers should be well
kept, including the chiefs from all systems, specialists from Y2K Project, full-time &
part-time employees.
Business clients: offering help to our clients if they have any problem of Y2K, ex:
EDI, Mail system, Fax Server
etc.
Non-information systems
Manufacture, produce, storage and equipment: Manufacturing systems, control of
manufacturing programs, robot, auto-controlled production, package, transfer stops and
systems of central-control are included.
Instruments for inspecting products: Various analytic or measured instruments &
experiment ones are included.
Adjacent environment: Fire alarm system, security system, electric-power control,
lightening, parking-lot system, elevator, material-control, waste water, environmental
protection
etc are included.
Development of new equipment and system: Designed assistance by computer, project
analytic system, inspection system: & instrument for demonstration.
Products: Referring to our guarantee of products for clients, all products are under
testing.
Substantial steps
To label as an identification while passing through Y2K test.

RETURN TO TOP
- Risk Assessment
Analyzing business impact and rate of break down by assessment
from the inventory & rank them by influence on production. Their ranking will be done
in time in order to keep business on as usual.
Take out the items with date problem from inventory: They are classified into 3 as follows:
- The items without clear dates at all
- The dated items without Y2 K problem
- The dated items with some problems of Y2K problem. (This is the main task for us
to complete)
Document the items with date problem: First of all we must know the influent degree of
the items with date problem, the put its influence on production on record. Its influence
will be measured by 5 degrees accordingly from original vendors to update programs or
substituted for others.

- Recovery Plan and Execution
All office resources will be available for recovery
plan. Which are handled by central information. The departments only need to follow their
operation. About the rest part which have to be repaired, we may ask help from other
departments or try to get some similar information from network to shorten our working
time. All necessary labor resources will be available from the inventory. Labor resource
is part of recovery plan too.
Recovery plan is concluded to be elimination, renew, recovery, amendment, accordingly.
The steps for recovery plan are:
According to the data Risk assessment, Recovery plan is arranged by risk ranking to help
vendors complete recovery.
Do our best to repair those that are still workable. Any renew or elimination shall be
followed companys plan & cost.
Some independent facilities can be changed on time if necessary. The prerequisite is to
know Y2K influence from original vendors and have Recovery plan first, then follow
companys decision to make any amendments if needed.
- Contingency Plan
Emergency plan is executing together with Y2K Project, but
based on not influencing business operation. Standard operation process, training &
substituted equipment are included in emergency plan.
Steps:
- Confirming the failures : Controlled and executed by Recovery plan, we pick out those
which cannot be repaired right away or still under recovery.
- The influence of failure assessment: Well complete this failure assessment
according to prior influent assessment & the percentage of well-done recovery, except
those which have been 100% repaired to be workable.
- Emergency substitute: The following will be taken if necessary: changing auto-controller
into hand-made. Managing stocks of raw materials and products, substituting products,
labor assisting etc. consideration. Alls completed by documentation.
Testing The computer will imitate future dates to set up a separate testing
system, ex: Checking the input date over the year of 2000 or not. Updating automatically
or not. No matter the guaranty of products from vendors is available or not, the testing
proposal should be presented. The details of testing will be put on record to make sure
their appropriate testing process and results. They also can be sent to our clients for
identifying Y2K test ready. Here are 3 steps:
- Non-information system: product information should be gotten from vendors first. All
testing & possible results should be confirmed as well. Then the date will be set in
peril of Y2K for testing if the internal system is with timing or mercury battery. The
detail of testing will be recorded. In order to get better solution any difference will be
reconfirmed with vendors.
- Systematic environment: The purpose of testing aims to make sure all hardware &
software without any Y2K problem. The data exchange will be able to continue under such an
environment while the year of 2000 comes. Testing is in 3 steps as follows:
- All works at present set-up dates.
- Test computers on and off under dangerous dates of Y2K.
- Test systems in the interim of Y2K (ex: 1999/12/31 23: 55) wait and see after 10 minutes
if the system environment changes.
- Applied system
- Set-up of data testing: Take out some trade records from old files & modify their
operation flow with dangerous dates of Y2Kfor testing Notice that its interim should be
between the years of 1999 & 2000.
Test Operation Flow:
Non-It System

Test Operation Flow: Systematic Environment

Test Operation Flow: Application System

- Internal Auditing
Executive: Team of Central Y2K
(1-1) The Purpose of Y2K Project.
Surely to promote & put Y2K Project in action through internal operation in order
to make all organizations & their additional departments discover blind spots while
working and offer the solutions to guide all departments to complete companys well.
(1-2). The Objects of Y2K Project.
All organizations and their additional departments, including the factories and selling
site in TAIWAN, Mainland China, America, Singapore
etc.
(1-3). The Proposals of Internal Audit.
(1-3-1). The organization and job distribution of internal audit team:
President: Executive secretary from Central Y2K, whos in charge of audited
objects and items.
Committee: Members from Central Y2K, who are in charge of confirmation of audited dates
upon attendance, the data-searching from audited departments & audited reports,
(1-3-2). Internal audit process

(1-3-3). Internal audit details
(1-3-3-1). The tasks being executed from central Y2K
(1-3-3-2). All listed tasks on controlled form of Y2K Project
(1-3-4). Internal audit procedures
(1-3-4-1). Paper audit: The confirmation of the data from all organizations and its
departments one punctual and completed.
(1-3-4-2). Attendance audit:
(1-3-4-2-1) Monthly audit: Once a month punctually.
(1-3-4-2-2) Casual audit: available at any time if necessary.
(1-4). The Correspondence between All Organizations & Departments. All audited
items must be identified and well-informed to audited authorities, including all necessary
documents & time. Attendance participates have to be applied in advance if necessary.
(1-5). The Relative forms.
Controlled procedure forms of Y2K project, internal audit records & inspection
forms.
- Y2K Project Progress

- Y2K Initial Budget
Initial budget --- NO LIMIT
RETURN TO TOP
V. APPENDIX: HIGH RISK TEST DATES
| Item |
High Risk Date |
Test |
| 1 |
9/9/99 |
Many computer programs use 9999 instead of max value. |
| 2 |
30/2/1998
31/4/1998
1/13/1998
0/0/0000 |
Prove that these dates could not be set. |
| 3 |
31/12/1999 ~ 1/1/2000 |
Set time to be 31/12/1999, 23:59 (Fri.), then wait a moment
and check if time could become 1/1/2000 (Sat.) correctly. Turn off then turn on the power,
and check if all things are correct. |
| 4 |
28/2/2000 ~ 29/2/2000 |
Set time to be 28/2/2000 ; 23:59 (Mon.), then wait a moment
and check if the date changes correctly to 29/2/2000 (Tues.) correctly. Turn off then turn
on the power, and check if all things are correct. |
| 5 |
29/2/2000 ~ 1/3/2000 |
Set time to 29/2/2000 23:59 (Tue.), then wait a moment and
check if the date changes correctly to 1/3/2000 (Wed.). |
| 6 |
31/12/2000 ~ 1/1/2001 |
Set time to 31/12/2000 23:59 (Sun.), then wait a moment and
check if the date changes correctly to 1/1/2001 (Mon.) correctly. |
| 7 |
28/2/2001 ~ 1/3/2001 |
Set time to 28/2/2001 23:59 (Wed.), then wait a moment and
check if the date changes correctly to 1/3/2001 (Through) correctly. |
| 8 |
28/2/2002 ~ 1/3/2002 |
Set time to 28/2/2002 23:59 (Through), then wait a moment and
check if the date changes correctly to 1/3/2002 (Fri.) correctly. |
| 9 |
28/2/2003 ~ 1/3/2003 |
Set time to 28/2/2003 23:59 (Fri.), then wait a moment and
check if the date changes correctly to 1/3/2003 (Sat.) correctly. |
10 |
28/2/2004 ~ 29/2/2004 |
Set time to 28/2/2004 23:59 (Sat.), then wait a moment and
check if the date changes correctly to 29/2/2004 (Sun.) correctly. |
11 |
10/1/00 |
Set time to 10/1/2000 00:01, check if the date section
displays the 2-digit day correctly. |
| 12 |
10/10/00 |
Set time to 10/10/2000 00:01, check if the time could Display
2-digit day correctly. |
RETURN TO TOP INTRODUCTION GOAL STRATEGY ACTION APPENDIX
|